Warehouses 25 & 26 Electrical and special systems

Former General Storehouses - Verona

The project
Verona Property Fund - Former General Storehouses of Verona. Functional renovation, for office use, of Warehouses 25 and 26 (Building 09) - Executive project variance 1: Condominium parts and electrical and special systems for user DoBank.

Commissioning body

Torre SGR S.p.A.

Period

2018
Corpi illuminati Ex Magazzini Generali

Activities performed

Definition of the entire project documentation with the appointed designers.

Oversight and monitoring of construction progress concerning the tenders to be awarded.

Verification, control, and development of site activities compared to the project and the work assignments under the defined schedule.

Coordination of all site activities among Designers - Construction Management and Contractors.

IPC control and authorisation in agreement with the Director of Works.

R.V.E. Reverse Value Engineering®.

Sent suppliers

41

Received offers

20

Percentage / number of receipts

49%

R.V.E.® Start date

June 2018

R.V.E.® End date

03 July 2018

Overall number of days

23
Importo Progetto

€ 662.632,20

Project Total

Importo Reverse Value Engineering®

€ 420.685,66

Reverse Value Engineering® Fee

Reverse Value Engineering® Delta

€ 241.946,55

Delta RVE

Final optimisation

%

Optimised budget