Functional Renovation of “La Rotonda” Cooling Station and adjacent buildings, roofing system

Former General Storehouses - Verona

The project
Verona Property Fund - Former General Storehouses of Verona. Functional renovation of “La Rotonda” Cooling Station and adjacent buildings, roofing system.

Commissioning body

Torre SGR S.p.A.

Period

2018
la rotonda ex magazzini generali

Activities performed

Bills of quantities: upload and technical-economic assessment of original bills of quantities.

Crosscheck of quantities: crosscheck of the quantities given in the bills and the quantities checked in the design drawings.

Market survey: of construction materials and systems, comparison of costs and supplier estimates.

Price analysis: preparation of price analyses of every entry in the Bill of Quantities to determine the economic congruity of the cost of:

  • Labour
  • Materials
  • Transport
  • Rentals
  • General Expenses
  • Enterprise profit

Sent suppliers

5

Received offers

2

Percentage / number of receipts

40%

R.V.E.® Start date

28 April 2018

R.V.E.® End date

08 May 2018

Overall number of days

10
Importo Progetto

€ 1.377.012,57

Project Total

Importo Reverse Value Engineering®

€ 1.020.000,00

Reverse Value Engineering® Fee

Reverse Value Engineering® Delta

€ 357.012,57

Delta RVE

Final optimisation

%

Optimised budget

Let us build