Functional Renovation of warehouses 25 & 26 (department 09) lighting fixtures

Former General Storehouses - Verona

The project
Verona Property Fund - Former General Storehouses of Verona. Functional renovation, for office use, of Warehouses 25 and 26 (Building 09) - Executive project variance 1: Condominium parts and electrical and special systems for user DoBank.

Commissioning body

Torre SGR S.p.A.

Period

2018
Corpi illuminati Ex Magazzini Generali

Activities performed

Definition of the entire project documentation with the appointed designers.

Oversight and monitoring of construction progress concerning the tenders to be awarded.

Verification, control, and development of site activities compared to the project and the work assignments under the defined schedule.

Coordination of all site activities among Designers - Construction Management and Contractors.

IPC control and authorisation in agreement with the Director of Works.

R.V.E. Reverse Value Engineering®

Sent suppliers

10

Received offers

4

Percentage / number of receipts

40%

R.V.E.® Start date

July 2018

R.V.E.® End date

24 July 2018

Overall number of days

16
Importo Progetto

€ 904.415,58

Project Total

Importo Reverse Value Engineering®

€ 467.185,66

Reverse Value Engineering® Fee

Reverse Value Engineering® Delta

€ 437.229,92

Delta RVE

Final optimisation

%

Optimised budget

Let us build
a valuable partnership together.

Explore our other sites