Building renovation works of private residential unit in Via Albertario

Building - Housing Units - Rome Capital

The project
Fondo Cicerone Building Two - - Building renovation works of private residential unit - Via Albertario n.18-19-20-21 ROME.

Commissioning body

Fabrica Immobiliare SGR S.p.A.

Period

2022
Opere di riqualificazione di 76 unità immobiliari - Via Giovanni Andrea Badoero nn. 51-61

Activities performed

Uploading of estimated bills of quantities onto the system.

Performance of market surveys.

Call for tenders from suppliers of building materials and systems.

Technical/economic tabulation of the bids received.

Crosscheck of correspondences between technical specifications, materials, and construction systems and design requirements.

Value Engineering RVE® activities.

Sent suppliers

26

Received offers

15

Percentage / number of receipts

57%

R.V.E.® Start date

27 June 2022

R.V.E.® End date

22 July 2022

Overall number of days

25
Importo Progetto

€ 2.368.646,40

Project Total

Importo Reverse Value Engineering®

€ 2.064.591,26

Reverse Value Engineering® Fee

Reverse Value Engineering® Delta

€ 304.055,14

Delta RVE

Final optimisation

%

Optimised budget