Project for a two-storey underground car park and a ground level parking lot

Former General Storehouses - Verona

The project
Verona Property Fund - Former General Storehouses of Verona. Project for a two-storey underground car park in the area before the building 10 - Thermomechanical installations.

Commissioning body

Patrizia S.A.R.L.

Period

2019
Parcheggio a due piani interrati

Activities performed

Uploading of estimated bills of quantities onto the system.

Execution of market surveys.

Call for tenders from suppliers of building materials and systems.

Technical/economic tabulation of the bids received.

Crosscheck of correspondences between technical specifications, materials, and construction systems and design requirements.

R.V.E. Reverse Value Engineering®.

Sent suppliers

67

Received offers

43

Percentage / number of receipts

64%

R.V.E.® Start date

January 2019

R.V.E.® End date

17 January 2019

Overall number of days

12
Importo Progetto

€ 2.609.092,29

Project Total

Importo Reverse Value Engineering®

€ 1.954.166,38

Reverse Value Engineering® Fee

Reverse Value Engineering® Delta

€ 654.925,91

Delta RVE