Restyling of facades and common areas

Roma, RM - 21 Clivo Rutario street

The project
Cicerone Fund - Section TWO - Executive project ROME.

Commissioning body

Fabrica Immobiliare SGR S.p.A.

Period

2025

Activities performed

Uploading the estimated quantity survey to the system;

Conducting market research;

Request for Quotation (RFQ) to suppliers of construction materials and systems;

Technical and economic tabulation of the received offers

Verification of the correspondence between the technical specifications of materials and construction systems and the project requirements;

Value Engineering RVE® activities;

Metric verification.

Sent suppliers

59

Received offers

52

Percentage / number of receipts

88,13%

R.V.E.® Start date

20/01/2025

R.V.E.® End date

24/02/2025

Overall number of days

35

Final optimisation

%

Optimised budget