Functional renovation of the Cooling Station and adjacent electrical installation buildings

Former General Storehouses - Verona

The project
Verona Property Fund - Former General Storehouses of Verona. Functional renovation of “La Rotonda” Cooling Station and adjacent buildings – Electrical installation.

Commissioning body

Patrizia S.A.R.L.

Period

2019
Parcheggio a due piani interrati

Activities performed

Uploading of estimated bills of quantities onto the system.

Execution of market surveys.

Call for tenders from suppliers of building materials and systems.

Technical/economic tabulation of the bids received.

Crosscheck of correspondences between technical specifications, materials, and construction systems and design requirements.

R.V.E. Reverse Value Engineering®.

Sent suppliers

64

Received offers

38

Percentage / number of receipts

59%

R.V.E.® Start date

April 2019

R.V.E.® End date

02 May 2019

Overall number of days

21
Importo Progetto

€ 4.059.451,60

Project Total

Importo Reverse Value Engineering®

€ 2.519.167,63

Reverse Value Engineering® Fee

Reverse Value Engineering® Delta

€ 1.540.283,97

Delta RVE

Final optimisation

%

Optimised budget

Let us build